Asak Real Estate Development has 1 project registered with the Dubai Land Department and not yet complete. Of its 1 project finished since 2024, 0 finished by the planned date in the register.
Not yet complete
| Project | Community | Units | Planned completion | Progress |
|---|---|---|---|---|
| Golf Terrace Residences by ASAK | International Media Production Zone | 105 | Oct 2, 2027 | 5.07% |
Finished since 2024
| Project | Community | Planned | Completed |
|---|---|---|---|
| Al Serh Residences 11 by Asak Real Estate Development | Jumeirah Village Circle | Feb 28, 2025 | Jun 4, 2026 |
The planned date is the one in the register at completion, which may itself have been revised.