Deyaar off-plan projects in Dubai
Deyaar has 10 projects registered with the Dubai Land Department and not yet complete, 2 past the planned completion date. Of its 3 projects finished since 2024, 0 finished by the planned date in the register.
Registered under 2 company names: Deyaar Development, Deyaar Bay Real Estate Development.
Not yet complete
| Project | Community | Units | Planned completion | Progress |
|---|---|---|---|---|
| Tria by Deyaar | Silicon Oasis | 717 | Jun 30, 2025 | 94.11% |
| Mar Casa | Dubai Maritime City | 585 | Oct 31, 2026 | 56.45% |
| Elm at Park Five | International Media Production Zone | 532 | Jun 1, 2027 | 16.18% |
| Ember at Park Five | International Media Production Zone | 205 | Jun 1, 2027 | 18.24% |
| Neem at Park Five | International Media Production Zone | 145 | Dec 1, 2027 | 15.22% |
| Ivy at Park Five | International Media Production Zone | 210 | Dec 31, 2027 | 6.28% |
| Alder at Park Five | International Media Production Zone | 75 | Dec 31, 2027 | 6.07% |
| Downtown Residences | Business Bay | 524 | Dec 30, 2030 | 1.25% |
| Rosalia Residences | Al Furjan | 118 | 82.04% | |
| Eleve by Deyaar | Down Town Jabal Ali | 818 | 20.01% |
Finished since 2024
| Project | Community | Planned | Completed |
|---|---|---|---|
| Jannat | International Media Production Zone | Jun 4, 2026 | |
| Talia Residences | Al Furjan | Apr 30, 2025 | Jun 1, 2026 |
| Regalia | Business Bay | Dec 31, 2024 | Apr 29, 2026 |
| Amalia Residences | Al Furjan | Jan 31, 2025 | Nov 17, 2025 |
The planned date is the one in the register at completion, which may itself have been revised.