Lucky Aeon Real Estate Development has 1 project registered with the Dubai Land Department and not yet complete, 1 past the planned completion date. Of its 1 project finished since 2024, 0 finished by the planned date in the register.
Not yet complete
| Project | Community | Units | Planned completion | Progress |
|---|---|---|---|---|
| Lucky Oasis Residence | Jumeirah Village Circle | 144 | Jun 30, 2026 | 20% |
Finished since 2024
| Project | Community | Planned | Completed |
|---|---|---|---|
| Lucky Royale Residence | Jumeirah Village Circle | Dec 31, 2025 | Oct 14, 2026 |
The planned date is the one in the register at completion, which may itself have been revised.