North Dubailand Projects off-plan projects in Dubai

North Dubailand Projects has 2 projects registered with the Dubai Land Department and not yet complete. Of its 4 projects finished since 2024, 4 finished by the planned date in the register.

Not yet complete

ProjectCommunityUnitsPlanned completionProgress
La Tilia at Villanova Phase 1Wadi Al Safa 50Aug 21, 202813.75%
La Tilia at Villanova Phase 2Wadi Al Safa 50Aug 21, 202810.57%

Finished since 2024

ProjectCommunityPlannedCompleted
La Violeta 1Wadi Al Safa 5Feb 1, 2025Feb 1, 2025
La Rosa 6Wadi Al Safa 5Dec 1, 2024Dec 1, 2024
La Rosa 5Wadi Al Safa 5Aug 1, 2024Aug 1, 2024
La Violeta 2Wadi Al Safa 5Jul 1, 2024Jul 1, 2024

The planned date is the one in the register at completion, which may itself have been revised.