ORO24 Real Estate Development off-plan projects in Dubai

ORO24 Real Estate Development has 4 projects registered with the Dubai Land Department and not yet complete, 3 past the planned completion date. Of its 1 project finished since 2024, 0 finished by the planned date in the register.

Not yet complete

ProjectCommunityUnitsPlanned completionProgress
Elano by ORO24Arjan339Oct 1, 202570%
Levanto by ORO24Jumeirah Village Circle579Dec 8, 202566%
Kyoto by ORO24Arjan708Sep 20, 202616.96%
Albero by ORO24Liwan119244.81%

Finished since 2024

ProjectCommunityPlannedCompleted
Torino by ORO24ArjanJul 8, 2024Oct 15, 2025

The planned date is the one in the register at completion, which may itself have been revised.