Westar Properties off-plan projects in Dubai
Westar Properties has 1 project registered with the Dubai Land Department and not yet complete. Of its 1 project finished since 2024, 1 finished by the planned date in the register.
Not yet complete
| Project | Community | Units | Planned completion | Progress |
|---|---|---|---|---|
| Westar Altair | Dubai South Residential District | 56 | May 31, 2027 | 62.86% |
Finished since 2024
| Project | Community | Planned | Completed |
|---|---|---|---|
| Celeste by Westar | Jumeirah Village Circle | Dec 31, 2025 | Dec 3, 2025 |
The planned date is the one in the register at completion, which may itself have been revised.