35.57%complete

Aero 1

Aero 1 is a building project in Dubai South Residential District, Dubai, by Bithaus Real Estate Development. The Dubai Land Department's register puts it at 35.57% complete, with planned completion on Jul 15, 2027.

Planned completion: Jul 15, 2027. Time left: 8 months

Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 3728), which also shows the latest inspection date and photos.

Facts

Status
Under construction
Official progress
35.57%, as published by the Dubai Land Department
Planned completion
Jul 15, 2027
Construction start
Jul 15, 2025
Units
48
Buildings
1
Developer
Bithaus Real Estate Development
Master developer
Dubai Aviation City Corporation
Community
Dubai South Residential District, in DLD's area Madinat Al Mataar
Escrow bank
First Abu Dhabi Bank
DLD project number
3728

The register describes it as: "RESIDENTIAL BUILDING (G+4+Roof)"

Progress as the register reported it

SinceProgressPlanned completion
Oct 29, 202635.57%Jul 15, 2027

Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.

Off-plan sales registered

12 off-plan sales in Aero 1 have been registered with the Dubai Land Department, worth AED 10.5 million in all, the first on Oct 10, 2025 and the latest on Oct 8, 2026. 4 of them in the last 90 days. The median price over the last 12 months was AED 14,424 per square meter (AED 1,340 per square foot).

Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.