Amazonia
Amazonia is a building project in Jaddaf Waterfront, Dubai, by Palladium Prime Real Estate Development. The Dubai Land Department's register puts it at 1.35% complete, with planned completion on Oct 30, 2027.
Planned completion: Oct 30, 2027. Time left: 1 year
Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 3595), which also shows the latest inspection date and photos.
Facts
- Status
- Under construction
- Official progress
- 1.35%, as published by the Dubai Land Department
- Planned completion
- Oct 30, 2027
- Construction start
- Oct 20, 2025
- Units
- 76
- Buildings
- 1
- Developer
- Palladium Prime Real Estate Development
- Master developer
- Dubai Properties
- Community
- Jaddaf Waterfront, in DLD's area Al Jadaf
- Escrow bank
- Abu Dhabi Islamic Bank
- DLD project number
- 3595
The register describes it as: "Residential Building (3B+G+12F+R)"
Progress as the register reported it
| Since | Progress | Planned completion |
|---|---|---|
| Oct 29, 2026 | 1.35% | Oct 30, 2027 |
Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.
Off-plan sales registered
26 off-plan sales in Amazonia have been registered with the Dubai Land Department, worth AED 35.3 million in all, the first on Feb 16, 2026 and the latest on Sep 16, 2026. 6 of them in the last 90 days. The median price over the last 12 months was AED 18,528 per square meter (AED 1,721 per square foot).
Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.
More in Jaddaf Waterfront
- Boutique 23 Jaddaf Waterfront · Continental Investments Lmd 64.86%No planned date in the register
- Binghatti Moonlight Jaddaf Waterfront · Binghatti 19.24%Planned Jun 15, 2026, 5 months ago
- Binghatti Twilight Jaddaf Waterfront · Binghatti 55.41%Planned Apr 30, 2026, 6 months ago
- Montage Jaddaf Waterfront · Key Mavens Montage Real Estate Development 40%Planned completion Aug 31, 2027
- Art Bay West Jaddaf Waterfront · Ellington 9.11%No planned date in the register
- Val by Kasco Jaddaf Waterfront · Kasco Real Estate Development 72.55%Planned completion Dec 30, 2026