Off-plan projects in The World
7 projects in The World are registered and not yet complete, 4 of them past the planned completion date, according to the Dubai Land Department.
Not yet complete
| Project | Developer | Units | Planned completion | Progress |
|---|---|---|---|---|
| The Heart of Europe 2 | T H O E Real Estate Development | 1,383 | Apr 30, 2025 | 93.42% |
| The Heart of Europe 1 | T H O E Real Estate Development | 0 | Sep 30, 2022 | 86.18% |
| The Heart of Europe | T H O E Real Estate Development | 0 | Sep 30, 2022 | 82.28% |
| Zaya Zuha Island | Zaya Zuha Island For Real Estate Development | 1 | Jun 30, 2025 | 81.1% |
| Sea Horse Villa | T H O E Real Estate Development | 0 | 50% | |
| Marbella Resort Hotel, a Vignette Collection world Islands Dubai | Marbella D W I Real Estate Development | 153 | 46.85% | |
| Amali Island | Amali Properties | 0 | Mar 31, 2027 | 16.37% |