70.05%complete

Ashton Park Residences the Second

Ashton Park Residences the Second is a building project in Jumeirah Village Circle, Dubai, by Ashton Real Estate Development. The Dubai Land Department's register puts it at 70.05% complete, with planned completion on Dec 31, 2025.

Planned completion was Dec 31, 2025. Time since: 10 months

Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 3263), which also shows the latest inspection date and photos.

Facts

Status
Past planned completion
Official progress
70.05%, as published by the Dubai Land Department
Planned completion
Dec 31, 2025
Construction start
Nov 1, 2024
Units
194
Buildings
1
Developer
Ashton Real Estate Development
Master developer
Jumeirah Village
Community
Jumeirah Village Circle, in DLD's area Al Barsha South Fourth
Escrow bank
Sharjah Islamic Bank
DLD project number
3263

The register describes it as: "G+P+5 Floors +Roof."

Progress as the register reported it

SinceProgressPlanned completion
Oct 29, 202670.05%Dec 31, 2025

Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.

Off-plan sales registered

201 off-plan sales in Ashton Park Residences the Second have been registered with the Dubai Land Department, worth AED 192 million in all, the first on Sep 30, 2024 and the latest on Oct 22, 2026. 1 of them in the last 90 days. The median price over the last 12 months was AED 20,677 per square meter (AED 1,921 per square foot).

Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.