Aura Central
Aura Central is a building project in Arjan, Dubai, by Aura Infinite Real Estate Development. The Dubai Land Department's register puts it at 100% complete (completed), with planned completion on Jul 14, 2027.
Completed on Sep 1, 2026, against a planned date of Jul 14, 2027.
Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 3327), which also shows the latest inspection date and photos.
Facts
- Status
- Completed
- Official progress
- 100%, as published by the Dubai Land Department
- Planned completion
- Jul 14, 2027
- Construction start
- Aug 1, 2024
- Units
- 38
- Buildings
- 1
- Developer
- Aura Infinite Real Estate Development
- Master developer
- Liwan
- Community
- Arjan, in DLD's area Al Barshaa South Third
- Escrow bank
- Dubai Islamic Bank
- DLD project number
- 3327
The register describes it as: "(BASEMENT + GROUND + 4 FLOOR) Commercial Building.The project designed to have a concrete structure and block with internal and external finishes."
Progress as the register reported it
| Since | Progress | Planned completion |
|---|---|---|
| Oct 29, 2026 | 100% | Jul 14, 2027 |
Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.
Off-plan sales registered
30 off-plan sales in Aura Central have been registered with the Dubai Land Department, worth AED 62.2 million in all, the first on Apr 30, 2025 and the latest on May 11, 2026. The median price over the last 12 months was AED 12,917 per square meter (AED 1,200 per square foot).
Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.
More in Arjan
- The central downtown Arjan · Aqua 10.48%Planned completion Mar 31, 2028
- Vincitore Dolce Vita Arjan · Vincitore 40%No planned date in the register
- Kyoto by ORO24 Arjan · ORO24 Real Estate Development 16.96%Planned Sep 20, 2026, 2 months ago
- Ashley Hills Arjan · Townx Real Estate Development 74.05%Planned completion Mar 31, 2027
- Butterfly Arjan · Desert Falcon Real Estate Development 7.65%Planned completion Jan 31, 2029
- Marquis One Arjan · Marquis Home Developer 0.29%Planned completion Dec 31, 2028