Casa Vista Residence by Golden Woods
Casa Vista Residence by Golden Woods is a building project in Jumeirah Village Circle, Dubai, by Casa Vista & Golden Woods Developers. The Dubai Land Department's register puts it at 90.05% complete, with planned completion on Jun 30, 2026.
Planned completion was Jun 30, 2026. Time since: 4 months
Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 2998), which also shows the latest inspection date and photos.
Facts
- Status
- Past planned completion
- Official progress
- 90.05%, as published by the Dubai Land Department
- Planned completion
- Jun 30, 2026
- Construction start
- Mar 1, 2024
- Units
- 90
- Buildings
- 1
- Developer
- Casa Vista & Golden Woods Developers
- Master developer
- Jumeirah Village
- Community
- Jumeirah Village Circle, in DLD's area Al Barsha South Fourth
- Escrow bank
- Abu Dhabi Commercial Bank
- DLD project number
- 2998
The register describes it as: "B+G+5 Residential & Retail Building.The project designed to have a concrete structure and block with internal and external finishes."
Progress as the register reported it
| Since | Progress | Planned completion |
|---|---|---|
| Oct 29, 2026 | 90.05% | Jun 30, 2026 |
Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.
Off-plan sales registered
81 off-plan sales in Casa Vista Residence by Golden Woods have been registered with the Dubai Land Department, worth AED 91.9 million in all, the first on Jun 17, 2024 and the latest on Oct 21, 2026. 3 of them in the last 90 days. The median price over the last 12 months was AED 15,931 per square meter (AED 1,480 per square foot).
Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.
More in Jumeirah Village Circle
- Serenz by Danube Jumeirah Village Circle · Danube 0.08%Planned completion Dec 31, 2029
- Auresta Tower Jumeirah Village Circle · Tiger 4.44%Planned completion Dec 31, 2028
- Binghatti Circle Jumeirah Village Circle · Binghatti 22.1%Planned completion May 31, 2027
- Elitz 2 by Danube Jumeirah Village Circle · Danube 20.01%No planned date in the register
- Maimoon Gardens Jumeirah Village Circle · Fakhruddin 78.02%Planned Dec 31, 2025, 10 months ago
- Binghatti Amberhall Jumeirah Village Circle · Binghatti 70.01%Planned Feb 28, 2026, 8 months ago