Facts

Status
Under construction
Official progress
3.14%, as published by the Dubai Land Department
Planned completion
May 19, 2028
Construction start
May 20, 2025
Units
121
Buildings
1
Developer
Aldhana Real Estate Development
Master developer
Jumeirah Village
Community
Jumeirah Village Circle, in DLD's area Al Barsha South Fourth
DLD project number
3572

The register describes it as: "G+5P+13Floors"

Progress as the register reported it

SinceProgressPlanned completion
Oct 29, 20263.14%May 19, 2028

Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.

Off-plan sales registered

27 off-plan sales in Celestara Residences have been registered with the Dubai Land Department, worth AED 16 million in all, the first on Sep 11, 2025 and the latest on Mar 5, 2026. The median price over the last 12 months was AED 18,590 per square meter (AED 1,727 per square foot).

Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.