Creek Views
Creek Views is a building project in Jaddaf Waterfront, Dubai, by Iraz Real Estate Development. The Dubai Land Department's register puts it at 38.8% complete.
The register gives no planned completion date for this project.
Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 3026), which also shows the latest inspection date and photos.
Facts
- Status
- Under construction
- Official progress
- 38.8%, as published by the Dubai Land Department
- Construction start
- May 15, 2024
- Units
- 108
- Buildings
- 1
- Developer
- Iraz Real Estate Development
- Master developer
- Culture Village
- Community
- Jaddaf Waterfront, in DLD's area Al Jadaf
- Escrow bank
- Emirates Islamic Bank
- DLD project number
- 3026
The register describes it as: "Residential building (2B+G+14+Roof)"
Progress as the register reported it
| Since | Progress | Planned completion |
|---|---|---|
| Oct 29, 2026 | 38.8% |
Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.
Off-plan sales registered
96 off-plan sales in Creek Views have been registered with the Dubai Land Department, worth AED 174 million in all, the first on Sep 5, 2024 and the latest on Oct 20, 2026. 1 of them in the last 90 days. The median price over the last 12 months was AED 17,079 per square meter (AED 1,587 per square foot).
Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.
More in Jaddaf Waterfront
- Boutique 23 Jaddaf Waterfront · Continental Investments Lmd 64.86%No planned date in the register
- Binghatti Moonlight Jaddaf Waterfront · Binghatti 19.24%Planned Jun 15, 2026, 5 months ago
- Binghatti Twilight Jaddaf Waterfront · Binghatti 55.41%Planned Apr 30, 2026, 6 months ago
- Montage Jaddaf Waterfront · Key Mavens Montage Real Estate Development 40%Planned completion Aug 31, 2027
- Art Bay West Jaddaf Waterfront · Ellington 9.11%No planned date in the register
- Val by Kasco Jaddaf Waterfront · Kasco Real Estate Development 72.55%Planned completion Dec 30, 2026