Damac Hills-Bel Air
Damac Hills-Bel Air is a villa project in Damac Hills, Dubai, by Damac Crescent Properties. The Dubai Land Department's register puts it at 100% complete (completed), with planned completion on Feb 29, 2024.
Completed on Feb 29, 2024, against a planned date of Feb 29, 2024.
Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 2236), which also shows the latest inspection date and photos.
Facts
- Status
- Completed
- Official progress
- 100%, as published by the Dubai Land Department
- Planned completion
- Feb 29, 2024
- Construction start
- Jun 8, 2021
- Developer
- Damac Crescent Properties
- Master developer
- Dubai Land Residences
- Community
- Damac Hills, in DLD's area Al Hebiah Third
- Escrow bank
- Abu Dhabi Commercial Bank
- DLD project number
- 2236
The register describes it as: "The project consists of 215 villas as (G+1) & (G+ 2) located at Al Hebiah Third. The Villas are designed to have a concrete structure and block with Internal and external finishes."
Progress as the register reported it
| Since | Progress | Planned completion |
|---|---|---|
| Oct 29, 2026 | 100% | Feb 29, 2024 |
Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.
More in Damac Hills
- Damac District Damac Hills · Damac 4.07%Planned completion Mar 30, 2029
- Damac Hills - Golf Greens 2 Damac Hills · Damac 45.21%No planned date in the register
- Damac Hills - Golf Greens 1 Damac Hills · Damac 40.52%Planned completion Mar 30, 2027
- Damac Hills - Golf Gate 2 Damac Hills · Damac 80.35%No planned date in the register
- Damac Hills - Gems Estates 1 Damac Hills · Damac 48.83%Planned completion Nov 30, 2026
- Damac Hills - Gems Estates 2 Damac Hills · Damac 62.64%Planned Sep 15, 2024, 2 years 2 months ago
More by Damac
- Aykon City 3 Business Bay · Damac 31.35%Planned completion Dec 30, 2027
- Damac Bay Dubai Harbour · Damac 33.76%Planned completion Jan 15, 2027
- Chelsea Residences 2 by Damac Dubai Maritime City · Damac 5.44%Planned completion Dec 31, 2029
- Damac Riverside Views - Capri 1 Dubai Investment Park Second · Damac 8.18%Planned completion Mar 31, 2029
- Damac Riverside Views - Azure 2 Dubai Investment Park Second · Damac 5.8%Planned completion Mar 31, 2029
- Chelsea Residences by Damac Dubai Maritime City · Damac 5.19%Planned completion Dec 31, 2029