Damac Hills - Cavalli Estates is a villa project in Damac Hills, Dubai, by Damac Crescent Properties. The Dubai Land Department's register puts it at 100% complete (completed), with planned completion on Dec 31, 2024.
Completed on May 13, 2026, against a planned date of Dec 31, 2024.
Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 2389), which also shows the latest inspection date and photos.
Facts
- Status
- Completed
- Official progress
- 100%, as published by the Dubai Land Department
- Planned completion
- Dec 31, 2024
- Construction start
- Jul 15, 2022
- Developer
- Damac Crescent Properties
- Community
- Damac Hills, in DLD's area Al Hebiah Third
- Escrow bank
- First Abu Dhabi Bank
- DLD project number
- 2389
The register describes it as: "Project consists of 41 Villas B+G + 2 villas located in Al Hebiah Third, Dubai. The villas are designed to have a concrete structure and block with internal and external finishes."
Progress as the register reported it
| Since | Progress | Planned completion |
|---|---|---|
| Oct 29, 2026 | 100% | Dec 31, 2024 |
Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.
More in Damac Hills
- Damac District Damac Hills · Damac 4.07%Planned completion Mar 30, 2029
- Damac Hills - Golf Greens 2 Damac Hills · Damac 45.21%No planned date in the register
- Damac Hills - Golf Greens 1 Damac Hills · Damac 40.52%Planned completion Mar 30, 2027
- Damac Hills - Golf Gate 2 Damac Hills · Damac 80.35%No planned date in the register
- Damac Hills - Gems Estates 1 Damac Hills · Damac 48.83%Planned completion Nov 30, 2026
- Damac Hills - Gems Estates 2 Damac Hills · Damac 62.64%Planned Sep 15, 2024, 2 years 2 months ago
More by Damac
- Aykon City 3 Business Bay · Damac 31.35%Planned completion Dec 30, 2027
- Damac Bay Dubai Harbour · Damac 33.76%Planned completion Jan 15, 2027
- Chelsea Residences 2 by Damac Dubai Maritime City · Damac 5.44%Planned completion Dec 31, 2029
- Damac Riverside Views - Capri 1 Dubai Investment Park Second · Damac 8.18%Planned completion Mar 31, 2029
- Damac Riverside Views - Azure 2 Dubai Investment Park Second · Damac 5.8%Planned completion Mar 31, 2029
- Chelsea Residences by Damac Dubai Maritime City · Damac 5.19%Planned completion Dec 31, 2029