Damac Lagoons - Malta (1)
Damac Lagoons - Malta (1) is a villa project in Al Hebiah Fifth, Dubai, by Island Oasis Properties. The Dubai Land Department's register puts it at 100% complete (completed), with planned completion on Sep 29, 2025.
Completed on Jun 19, 2026, against a planned date of Sep 29, 2025.
Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 2400), which also shows the latest inspection date and photos.
Facts
- Status
- Completed
- Official progress
- 100%, as published by the Dubai Land Department
- Planned completion
- Sep 29, 2025
- Construction start
- Aug 23, 2022
- Developer
- Island Oasis Properties
- Community
- Al Hebiah Fifth
- Escrow bank
- First Abu Dhabi Bank
- DLD project number
- 2400
The register describes it as: "686 x G+2 Villas , The project designed to have a concrete structure and block with internal and external finishes."
Progress as the register reported it
| Since | Progress | Planned completion |
|---|---|---|
| Oct 29, 2026 | 100% | Sep 29, 2025 |
Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.
More in Al Hebiah Fifth
- Damac Lagoons - Lagoon Views 1 Al Hebiah Fifth · Island Oasis Properties 55.58%No planned date in the register
- Damac Lagoons - Lagoon Views 2 Al Hebiah Fifth · Island Oasis Properties 52.27%No planned date in the register
- Damac Lagoons - Lagoon Views 3 Al Hebiah Fifth · Island Oasis Properties 39.18%No planned date in the register
- Damac Lagoons - Lagoon Views 4 Al Hebiah Fifth · Island Oasis Properties 42.17%No planned date in the register
- Damac Lagoons - Lagoon Views 9 Al Hebiah Fifth · Island Oasis Properties 47.29%Planned completion Mar 31, 2027
- Damac Lagoons - Lagoon Views 10 Al Hebiah Fifth · Island Oasis Properties 47.41%Planned completion Mar 31, 2027
More by Island Oasis Properties
- Damac Lagoons - Valencia DAMAC Lagoons · Island Oasis Properties 5.21%Planned completion Feb 28, 2028
- Damac Lagoons - Lagoon Views 13 DAMAC Lagoons · Island Oasis Properties 5.96%Planned completion Dec 31, 2027
- Piazza Roma DAMAC Lagoons · Island Oasis Properties 0.2%Planned completion Jun 30, 2030
- Damac Lagoons - Lagoon Views 11 DAMAC Lagoons · Island Oasis Properties 42.58%Planned completion Jun 30, 2027
- Damac Lagoons - Lagoon Views 12 DAMAC Lagoons · Island Oasis Properties 36.53%Planned completion Jun 30, 2027
- Damac Lagoons - Lagoon Views 7 Al Hebiah Fifth · Island Oasis Properties 44.89%No planned date in the register