36.54%complete

Damac Sun City

Damac Sun City is a villa project in Al Yelayiss 1, Dubai, by Damac Elite Investment Co. The Dubai Land Department's register puts it at 36.54% complete, with planned completion on Mar 30, 2028.

Planned completion: Mar 30, 2028. Time left: 1 year 5 months

Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 3268), which also shows the latest inspection date and photos.

Facts

Status
Under construction
Official progress
36.54%, as published by the Dubai Land Department
Planned completion
Mar 30, 2028
Construction start
Dec 1, 2024
Developer
Damac Elite Investment Co
Master developer
Shamal Estates
Community
Al Yelayiss 1
Escrow bank
Emirates NBD Bank
DLD project number
3268

The register describes it as: "Project consists of 770 Nos.of G+1+R Townhouses and villas located in Al Yalayis 1, Dubai. The units are designed to have a concrete structure and block with internal and external finishes."

Progress as the register reported it

SinceProgressPlanned completion
Oct 29, 202636.54%Mar 30, 2028

Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.