30.05%complete

Golden Woods Albab Views

Golden Woods Albab Views is a building project in Dubai South Residential District, Dubai, by A G W Real Estate Development. The Dubai Land Department's register puts it at 30.05% complete, with planned completion on Feb 28, 2027.

Planned completion: Feb 28, 2027. Time left: 4 months

Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 3591), which also shows the latest inspection date and photos.

Facts

Status
Under construction
Official progress
30.05%, as published by the Dubai Land Department
Planned completion
Feb 28, 2027
Construction start
Mar 1, 2025
Units
132
Buildings
1
Developer
A G W Real Estate Development
Master developer
Dubai Aviation City Corporation
Community
Dubai South Residential District, in DLD's area Madinat Al Mataar
Escrow bank
Abu Dhabi Islamic Bank
DLD project number
3591

The register describes it as: "G+4+R Residential Building"

Progress as the register reported it

SinceProgressPlanned completion
Oct 29, 202630.05%Feb 28, 2027

Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.

Off-plan sales registered

67 off-plan sales in Golden Woods Albab Views have been registered with the Dubai Land Department, worth AED 48.3 million in all, the first on Jul 15, 2025 and the latest on Oct 15, 2026. 2 of them in the last 90 days. The median price over the last 12 months was AED 14,828 per square meter (AED 1,378 per square foot).

Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.