1.88%complete

Jad 288

Jad 288 is a building project in Jumeirah Garden City, Dubai, by Jad Global Real Estate Development. The Dubai Land Department's register puts it at 1.88% complete, with planned completion on Dec 31, 2027.

Planned completion: Dec 31, 2027. Time left: 1 year 2 months

Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 3798), which also shows the latest inspection date and photos.

Facts

Status
Under construction
Official progress
1.88%, as published by the Dubai Land Department
Planned completion
Dec 31, 2027
Construction start
Dec 1, 2025
Units
222
Buildings
3
Developer
Jad Global Real Estate Development
Master developer
Meraas Estates
Community
Jumeirah Garden City, in DLD's area Al Satwa
Escrow bank
Dubai Islamic Bank
DLD project number
3798

The register describes it as: "3 Buildings of G+2P+8+Roof"

Progress as the register reported it

SinceProgressPlanned completion
Oct 29, 20261.88%Dec 31, 2027

Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.

Off-plan sales registered

62 off-plan sales in Jad 288 have been registered with the Dubai Land Department, worth AED 87.8 million in all, the first on Jan 19, 2026 and the latest on Nov 3, 2026. 10 of them in the last 90 days. The median price over the last 12 months was AED 24,221 per square meter (AED 2,250 per square foot).

Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.