Joya Dorado Residence
Joya Dorado Residence is a building project in Arjan, Dubai, by Green Yard Propertes Development. The Dubai Land Department's register puts it at 100% complete (completed), with planned completion on Mar 30, 2025.
Completed on Aug 11, 2026, against a planned date of Mar 30, 2025.
Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 2485), which also shows the latest inspection date and photos.
Facts
- Status
- Completed
- Official progress
- 100%, as published by the Dubai Land Department
- Planned completion
- Mar 30, 2025
- Construction start
- Nov 1, 2022
- Units
- 422
- Buildings
- 1
- Developer
- Green Yard Propertes Development
- Master developer
- Liwan
- Community
- Arjan, in DLD's area Al Barshaa South Third
- DLD project number
- 2485
The register describes it as: "B+G+2P+13+R, the project designed to have a concrete structure and block with internal and external finishes."
Progress as the register reported it
| Since | Progress | Planned completion |
|---|---|---|
| Oct 29, 2026 | 100% | Mar 30, 2025 |
Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.
Off-plan sales registered
519 off-plan sales in Joya Dorado Residence have been registered with the Dubai Land Department, worth AED 348 million in all, the first on Jan 11, 2023 and the latest on Jul 13, 2026. The median price over the last 12 months was AED 14,278 per square meter (AED 1,326 per square foot).
Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.
More in Arjan
- The central downtown Arjan · Aqua 10.48%Planned completion Mar 31, 2028
- Vincitore Dolce Vita Arjan · Vincitore 40%No planned date in the register
- Kyoto by ORO24 Arjan · ORO24 Real Estate Development 16.96%Planned Sep 20, 2026, 2 months ago
- Ashley Hills Arjan · Townx Real Estate Development 74.05%Planned completion Mar 31, 2027
- Butterfly Arjan · Desert Falcon Real Estate Development 7.65%Planned completion Jan 31, 2029
- Marquis One Arjan · Marquis Home Developer 0.29%Planned completion Dec 31, 2028