La Boutique
La Boutique is a building project in Jaddaf Waterfront, Dubai, by Continental Investments Lmd. The Dubai Land Department's register puts it at 52.5% complete, with planned completion on Dec 31, 2026.
Planned completion: Dec 31, 2026. Time left: 2 months
Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 3120), which also shows the latest inspection date and photos.
Facts
- Status
- Under construction
- Official progress
- 52.5%, as published by the Dubai Land Department
- Planned completion
- Dec 31, 2026
- Construction start
- Jul 1, 2024
- Units
- 119
- Buildings
- 1
- Developer
- Continental Investments Lmd
- Master developer
- Dubai Properties
- Community
- Jaddaf Waterfront, in DLD's area Al Jadaf
- Escrow bank
- Sharjah Islamic Bank
- DLD project number
- 3120
The register describes it as: "4B+G+15 residential building. The project designed to have a concrete structure and block with internal and external finishes."
Progress as the register reported it
| Since | Progress | Planned completion |
|---|---|---|
| Oct 29, 2026 | 52.5% | Dec 31, 2026 |
Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.
Off-plan sales registered
121 off-plan sales in La Boutique have been registered with the Dubai Land Department, worth AED 137 million in all, the first on Sep 13, 2024 and the latest on Oct 27, 2026. 1 of them in the last 90 days. The median price over the last 12 months was AED 18,066 per square meter (AED 1,678 per square foot).
Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.
More in Jaddaf Waterfront
- Boutique 23 Jaddaf Waterfront · Continental Investments Lmd 64.86%No planned date in the register
- Binghatti Moonlight Jaddaf Waterfront · Binghatti 19.24%Planned Jun 15, 2026, 5 months ago
- Binghatti Twilight Jaddaf Waterfront · Binghatti 55.41%Planned Apr 30, 2026, 6 months ago
- Montage Jaddaf Waterfront · Key Mavens Montage Real Estate Development 40%Planned completion Aug 31, 2027
- Art Bay West Jaddaf Waterfront · Ellington 9.11%No planned date in the register
- Val by Kasco Jaddaf Waterfront · Kasco Real Estate Development 72.55%Planned completion Dec 30, 2026