Liv Maritime

Liv Maritime is a building project in Dubai Maritime City, Dubai, by L I V Maritime Real Estate Development. The Dubai Land Department's register puts it at 28.12% complete, with planned completion on Dec 30, 2028.

Planned completion: Dec 30, 2028. Time left: 2 years 2 months

Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 3391), which also shows the latest inspection date and photos.

Facts

Status
Under construction
Official progress
28.12%, as published by the Dubai Land Department
Planned completion
Dec 30, 2028
Construction start
Nov 5, 2024
Units
258
Buildings
1
Developer
L I V Maritime Real Estate Development
Master developer
Dubai Maritime City
Community
Dubai Maritime City, in DLD's area Madinat Dubai Almelaheyah
Escrow bank
Commercial Bank of Dubai(psc)
DLD project number
3391

The register describes it as: "B+G+48+R,The project designed to have a concrete structure and block with internal and external finishes."

Progress as the register reported it

SinceProgressPlanned completion
Oct 29, 202628.12%Dec 30, 2028

Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.

Off-plan sales registered

248 off-plan sales in Liv Maritime have been registered with the Dubai Land Department, worth AED 701 million in all, the first on May 15, 2025 and the latest on Aug 25, 2026. 7 of them in the last 90 days. The median price over the last 12 months was AED 29,793 per square meter (AED 2,768 per square foot).

Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.