Marquis Galleria is a building project in Arjan, Dubai, by Marquis Home Developer. The Dubai Land Department's register puts it at 100% complete (completed), with planned completion on Dec 31, 2024.
Completed on Apr 10, 2026, against a planned date of Dec 31, 2024.
Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 2591), which also shows the latest inspection date and photos.
Facts
- Status
- Completed
- Official progress
- 100%, as published by the Dubai Land Department
- Planned completion
- Dec 31, 2024
- Construction start
- Feb 1, 2023
- Units
- 126
- Buildings
- 1
- Developer
- Marquis Home Developer
- Master developer
- Liwan
- Community
- Arjan, in DLD's area Al Barshaa South Third
- Escrow bank
- Emirates Islamic Bank
- DLD project number
- 2591
The register describes it as: "B+G+9+Roof Residential Building,The project designed to have a concrete structure and block with internal and external finishes."
Progress as the register reported it
| Since | Progress | Planned completion |
|---|---|---|
| Oct 29, 2026 | 100% | Dec 31, 2024 |
Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.
Off-plan sales registered
130 off-plan sales in Marquis Galleria have been registered with the Dubai Land Department, worth AED 149 million in all, the first on May 16, 2023 and the latest on Apr 2, 2026. The median price over the last 12 months was AED 16,058 per square meter (AED 1,492 per square foot).
Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.
More in Arjan
- The central downtown Arjan · Aqua 10.48%Planned completion Mar 31, 2028
- Vincitore Dolce Vita Arjan · Vincitore 40%No planned date in the register
- Kyoto by ORO24 Arjan · ORO24 Real Estate Development 16.96%Planned Sep 20, 2026, 2 months ago
- Ashley Hills Arjan · Townx Real Estate Development 74.05%Planned completion Mar 31, 2027
- Butterfly Arjan · Desert Falcon Real Estate Development 7.65%Planned completion Jan 31, 2029
- Marquis One Arjan · Marquis Home Developer 0.29%Planned completion Dec 31, 2028