ME DO RE Business is a building project in DMCC Master Community, Dubai, by ME DO RE Properties. The Dubai Land Department's register puts it at 24.47% complete, with planned completion on Sep 20, 2029.
Planned completion: Sep 20, 2029. Time left: 2 years 10 months
Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 3409), which also shows the latest inspection date and photos.
Facts
- Status
- Under construction
- Official progress
- 24.47%, as published by the Dubai Land Department
- Planned completion
- Sep 20, 2029
- Construction start
- Nov 15, 2025
- Units
- 293
- Buildings
- 1
- Developer
- ME DO RE Properties
- Master developer
- Dubai Multi Commodities Center
- Community
- DMCC Master Community, in DLD's area Al Thanyah Fifth
- Escrow bank
- Commercial Bank of Dubai(psc)
- DLD project number
- 3409
The register describes it as: "Commercial Tower Development located at Jumeirah Lakes Towers. The building is designed as 4B+1UB+G+39Floor+1 Mech Floor+ Roof+ Upper Roof Commercial Tower located on Plot No. H1 3930899, the building formed in a concrete structure, currently built until the eleventh floor, internal blocks with and an external curtain wall glazing system. The units will be handed over as core and shell construction."
Progress as the register reported it
| Since | Progress | Planned completion |
|---|---|---|
| Oct 29, 2026 | 24.47% | Sep 20, 2029 |
Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.
Off-plan sales registered
35 off-plan sales in ME DO RE Business have been registered with the Dubai Land Department, worth AED 184 million in all, the first on Jul 9, 2025 and the latest on Jun 11, 2026. The median price over the last 12 months was AED 38,607 per square meter (AED 3,587 per square foot).
Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.
More in DMCC Master Community
- Seven City JLT DMCC Master Community · Seven Tides 28.37%Planned Nov 24, 2025, 11 months ago
- Diamondz by Danube DMCC Master Community · Danube 18.5%No planned date in the register
- Verde by Sobha DMCC Master Community · Sobha 85%Planned completion Jun 30, 2027
- Mercer House DMCC Master Community · Eln Properties Development 18.11%Planned completion Jul 31, 2027
- Viewz 1 by Danube DMCC Master Community · Danube 66.47%Planned Jun 30, 2026, 4 months ago
- Viewz 2 by Danube DMCC Master Community · Danube 65.01%Planned Jun 30, 2026, 4 months ago