51%complete

Mohammed Bin Rashid Al Maktoum City -District One West - Phase 2

Mohammed Bin Rashid Al Maktoum City -District One West - Phase 2 is a villa project in Ghadeer Al tair, Dubai, by Meydan Group. The Dubai Land Department's register puts it at 51% complete, with planned completion on Nov 19, 2027.

Planned completion: Nov 19, 2027. Time left: 1 year

Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 3200), which also shows the latest inspection date and photos.

Facts

Status
Under construction
Official progress
51%, as published by the Dubai Land Department
Planned completion
Nov 19, 2027
Construction start
Nov 20, 2024
Developer
Meydan Group
Community
Ghadeer Al tair
Escrow bank
Dubai Islamic Bank
DLD project number
3200

The register describes it as: "Mohammed Bin Rashid Al Maktoum City -District One West ? Phase 2 will be a gated community with a Signature Crystal Lagoon as a central feature. The development consists of 229 villas following one of the 10 prototypes. There are 3 types of 4,5 & 6 bedrooms. The community will have all the necessary amenities including clubhouse, retail facilities, etc."

Progress as the register reported it

SinceProgressPlanned completion
Oct 29, 202651%Nov 19, 2027

Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.