100%complete

Mudon Al Ranim 2

Mudon Al Ranim 2 is a villa community in Mudon, Dubai, by Mdn Real Estate. The Dubai Land Department's register puts it at 100% complete (completed), with planned completion on May 28, 2025.

Completed on Dec 31, 2025, against a planned date of May 28, 2025.

Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 2419), which also shows the latest inspection date and photos.

Facts

Status
Completed
Official progress
100%, as published by the Dubai Land Department
Planned completion
May 28, 2025
Construction start
Sep 5, 2022
Villas
176
Developer
Mdn Real Estate
Master developer
Dubai Properties
Community
Mudon, in DLD's area Al Hebiah Sixth
Escrow bank
Commercial Bank of Dubai(psc)
DLD project number
2419

The register describes it as: "The project consists of 176 townhouse G+1 & G+2 (mix of 4 bed and 3 bed units)"

Progress as the register reported it

SinceProgressPlanned completion
Oct 29, 2026100%May 28, 2025

Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.

Off-plan sales registered

236 off-plan sales in Mudon Al Ranim 2 have been registered with the Dubai Land Department, worth AED 579 million in all, the first on Sep 29, 2022 and the latest on Jun 27, 2025.

Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.