Murooj Alfurjan West is a villa project in Al Furjan, Dubai, by Alfurjan ( L.L.C ). The Dubai Land Department's register puts it at 100% complete (completed), with planned completion on Sep 24, 2024.
Completed on Jun 30, 2024, against a planned date of Sep 24, 2024.
Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 2273), which also shows the latest inspection date and photos.
Facts
- Status
- Completed
- Official progress
- 100%, as published by the Dubai Land Department
- Planned completion
- Sep 24, 2024
- Construction start
- Nov 30, 2021
- Developer
- Alfurjan ( L.L.C )
- Master developer
- Nakheel .(P J S C)
- Community
- Al Furjan, in DLD's area Jabal Ali First
- Escrow bank
- Dubai Islamic Bank
- DLD project number
- 2273
The register describes it as: "the project consists of plot no. AF2-PKG-14: 360Residential Townhouses (G+1) + 2 club houses + 2 gate houses + security room (Ground only) plot no. AF2-PKG-15 161Residential Townhouses Type A&B (G+1) + club house + gate house + security room (Ground only).The project designed to have a concrete structure and block with internal and external finishes."
Progress as the register reported it
| Since | Progress | Planned completion |
|---|---|---|
| Oct 29, 2026 | 100% | Sep 24, 2024 |
Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.
More in Al Furjan
- SPARKLZ by Danube Al Furjan · Danube 7.75%Planned completion May 31, 2028
- Azizi Jewel Al Furjan · Azizi 43.03%No planned date in the register
- Azizi Neila Al Furjan · Azizi 38.53%Planned completion Jul 30, 2027
- The Stella Residences Al Furjan · Algouta Properties 71.06%Planned Dec 1, 2025, 11 months ago
- Azizi Sikander Al Furjan · Azizi 2%Planned completion Jun 17, 2027
- Raffi by Azizi Al Furjan · Azizi 2%Planned completion Jan 15, 2028