100%complete

NAS3

NAS3 is a building project in Arjan, Dubai, by Rabdan Real Estate Development. The Dubai Land Department's register puts it at 100% complete (completed), with planned completion on Feb 1, 2026.

Completed on Apr 8, 2026, against a planned date of Feb 1, 2026.

Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 2760), which also shows the latest inspection date and photos.

Facts

Status
Completed
Official progress
100%, as published by the Dubai Land Department
Planned completion
Feb 1, 2026
Construction start
Oct 1, 2023
Units
288
Buildings
1
Developer
Rabdan Real Estate Development
Master developer
Dubai Properties
Community
Arjan, in DLD's area Al Barshaa South Third
Escrow bank
Emirates Islamic Bank
DLD project number
2760

The register describes it as: "G+2P+12 ,B is water tank,284 units Residential+Retail.The project designed to have a concrete structure and block with internal and external finishes."

Progress as the register reported it

SinceProgressPlanned completion
Oct 29, 2026100%Feb 1, 2026

Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.

Off-plan sales registered

290 off-plan sales in NAS3 have been registered with the Dubai Land Department, worth AED 300 million in all, the first on Feb 1, 2024 and the latest on Mar 24, 2026. The median price over the last 12 months was AED 15,495 per square meter (AED 1,440 per square foot).

Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.