Oakyard Residences
Oakyard Residences is a building project in Jumeirah Village Circle, Dubai, by One Yard Real Estate Development. The Dubai Land Department's register puts it at 26.16% complete, with planned completion on Feb 15, 2027.
Planned completion: Feb 15, 2027. Time left: 3 months
Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 3473), which also shows the latest inspection date and photos.
Facts
- Status
- Under construction
- Official progress
- 26.16%, as published by the Dubai Land Department
- Planned completion
- Feb 15, 2027
- Construction start
- Sep 11, 2024
- Units
- 191
- Buildings
- 1
- Developer
- One Yard Real Estate Development
- Master developer
- Jumeirah Village
- Community
- Jumeirah Village Circle, in DLD's area Al Barsha South Fourth
- Escrow bank
- Mashreq Bank Psc
- DLD project number
- 3473
The register describes it as: "RESIDENTIAL BUILDING (UG+G+4P+19+R) with retail at Ground floor ."
Progress as the register reported it
| Since | Progress | Planned completion |
|---|---|---|
| Oct 29, 2026 | 26.16% | Feb 15, 2027 |
Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.
Off-plan sales registered
123 off-plan sales in Oakyard Residences have been registered with the Dubai Land Department, worth AED 131 million in all, the first on May 14, 2025 and the latest on Nov 3, 2026. 25 of them in the last 90 days. The median price over the last 12 months was AED 15,762 per square meter (AED 1,464 per square foot).
Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.
More in Jumeirah Village Circle
- Serenz by Danube Jumeirah Village Circle · Danube 0.08%Planned completion Dec 31, 2029
- Auresta Tower Jumeirah Village Circle · Tiger 4.44%Planned completion Dec 31, 2028
- Binghatti Circle Jumeirah Village Circle · Binghatti 22.1%Planned completion May 31, 2027
- Elitz 2 by Danube Jumeirah Village Circle · Danube 20.01%No planned date in the register
- Maimoon Gardens Jumeirah Village Circle · Fakhruddin 78.02%Planned Dec 31, 2025, 10 months ago
- Binghatti Amberhall Jumeirah Village Circle · Binghatti 70.01%Planned Feb 28, 2026, 8 months ago