100%complete

Orra the Embankment

Orra the Embankment is a building project in DMCC Master Community, Dubai, by Orra Real Estate Development. The Dubai Land Department's register puts it at 100% complete (completed), with planned completion on Aug 1, 2023.

Completed on Jan 29, 2026, against a planned date of Aug 1, 2023.

Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 360), which also shows the latest inspection date and photos.

Facts

Status
Completed
Official progress
100%, as published by the Dubai Land Department
Planned completion
Aug 1, 2023
Construction start
Dec 18, 2013
Units
464
Buildings
3
Developer
Orra Real Estate Development
Master developer
Dubai Multi Commodities Center
Community
DMCC Master Community, in DLD's area Al Thanyah Fifth
Escrow bank
Abu Dhabi Commercial Bank
DLD project number
360

The register describes it as: "PROJECT CONSISTS OF 4B+G+M+3P+44 MIXED USED TOWER LOCATED IN AL THANYAH FIFTH. THE APARTMENTS ARE DESIGNED TO HAVE A CONCRETE STRUCTURE AND BLOCK WITH INTERNAL AND EXTERNAL FINISHES."

Progress as the register reported it

SinceProgressPlanned completion
Oct 29, 2026100%Aug 1, 2023

Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.

Off-plan sales registered

509 off-plan sales in Orra the Embankment have been registered with the Dubai Land Department, worth AED 465 million in all, the first on Jun 5, 2009 and the latest on Dec 30, 2025. The median price over the last 12 months was AED 14,833 per square meter (AED 1,378 per square foot).

Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.