69.7%complete

Paradise One

Paradise One is a building project in Jumeirah Village Triangle, Dubai, by Danat Aldunia Real Estate Development. The Dubai Land Department's register puts it at 69.7% complete, with planned completion on Apr 15, 2027.

Planned completion: Apr 15, 2027. Time left: 5 months

Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 807), which also shows the latest inspection date and photos.

Facts

Status
Under construction
Official progress
69.7%, as published by the Dubai Land Department
Planned completion
Apr 15, 2027
Construction start
Oct 15, 2025
Units
121
Buildings
1
Developer
Danat Aldunia Real Estate Development
Master developer
Jumeirah Village
Community
Jumeirah Village Triangle, in DLD's area Al Barsha South Fifth
Escrow bank
Sharjah Islamic Bank
DLD project number
807

The register describes it as: "2 BASEMENTS (PARKING & SERVICES) + GROUND (COMMERCIAL, RESIDENTIAL, SERVICES, GYMNASIUM & SWIMMING POOL) + 4 TYPICAL (RESIDENTIAL) + GARDEN ROOF"

Progress as the register reported it

SinceProgressPlanned completion
Oct 29, 202669.7%Apr 15, 2027

Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.

Off-plan sales registered

54 off-plan sales in Paradise One have been registered with the Dubai Land Department, worth AED 24.8 million in all, the first on Apr 7, 2010 and the latest on Jan 27, 2020.

Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.

More in Jumeirah Village Triangle