Park Lane 2 by Heilbronn
Park Lane 2 by Heilbronn is a building project in Jumeirah Village Circle, Dubai, by Heilbronn Properties Development. The Dubai Land Department's register puts it at 100% complete (completed), with planned completion on Mar 31, 2026.
Completed on Feb 13, 2026, against a planned date of Mar 31, 2026.
Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 3291), which also shows the latest inspection date and photos.
Facts
- Status
- Completed
- Official progress
- 100%, as published by the Dubai Land Department
- Planned completion
- Mar 31, 2026
- Construction start
- Jun 16, 2024
- Units
- 83
- Buildings
- 1
- Developer
- Heilbronn Properties Development
- Master developer
- Nakheel .(P J S C)
- Community
- Jumeirah Village Circle, in DLD's area Al Barsha South Fourth
- Escrow bank
- Commercial Bank International
- DLD project number
- 3291
The register describes it as: "G+P+5 Floor Residential Building, JVC11IMRP002, Plot No. 1207, Al Barsha South Fourth, Dubai, U.A.E., The project designed to have a concrete structure and block with internal and external finishes."
Progress as the register reported it
| Since | Progress | Planned completion |
|---|---|---|
| Oct 29, 2026 | 100% | Mar 31, 2026 |
Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.
Off-plan sales registered
68 off-plan sales in Park Lane 2 by Heilbronn have been registered with the Dubai Land Department, worth AED 101 million in all, the first on Aug 12, 2025 and the latest on Feb 5, 2026. The median price over the last 12 months was AED 17,634 per square meter (AED 1,638 per square foot).
Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.
More in Jumeirah Village Circle
- Serenz by Danube Jumeirah Village Circle · Danube 0.08%Planned completion Dec 31, 2029
- Auresta Tower Jumeirah Village Circle · Tiger 4.44%Planned completion Dec 31, 2028
- Binghatti Circle Jumeirah Village Circle · Binghatti 22.1%Planned completion May 31, 2027
- Elitz 2 by Danube Jumeirah Village Circle · Danube 20.01%No planned date in the register
- Maimoon Gardens Jumeirah Village Circle · Fakhruddin 78.02%Planned Dec 31, 2025, 10 months ago
- Binghatti Amberhall Jumeirah Village Circle · Binghatti 70.01%Planned Feb 28, 2026, 8 months ago