84.23%complete

PELaGOS by IGO

PELaGOS by IGO is a building project in Dubai Marina, Dubai, by Digo Real Estate Development (br of Invest Group Overseas (L L C) ). The Dubai Land Department's register puts it at 84.23% complete, with planned completion on Mar 31, 2026.

Planned completion was Mar 31, 2026. Time since: 7 months

Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 3246), which also shows the latest inspection date and photos.

Facts

Status
Past planned completion
Official progress
84.23%, as published by the Dubai Land Department
Planned completion
Mar 31, 2026
Construction start
Dec 1, 2024
Units
296
Buildings
1
Developer
Digo Real Estate Development (br of Invest Group Overseas (L L C) )
Master developer
Emaar Development
Community
Dubai Marina, in DLD's area Marsa Dubai
Escrow bank
First Abu Dhabi Bank
DLD project number
3246

The register describes it as: "5B + G + 2P + Amenity Floor + 32 residential floor + 1 Mechanical + Roof.The project designed to have a concrete structure and block with internal and external finishes."

Progress as the register reported it

SinceProgressPlanned completion
Oct 29, 202684.23%Mar 31, 2026

Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.

Off-plan sales registered

277 off-plan sales in PELaGOS by IGO have been registered with the Dubai Land Department, worth AED 584 million in all, the first on Dec 20, 2024 and the latest on Oct 9, 2026. 1 of them in the last 90 days. The median price over the last 12 months was AED 31,639 per square meter (AED 2,939 per square foot).

Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.