5.6%complete

Peninsula Dubai Residences - Tower 1

Peninsula Dubai Residences - Tower 1 is a building project in Jumeirah Second, Dubai, by Dubai Peninsula. The Dubai Land Department's register puts it at 5.6% complete, with planned completion on Jan 8, 2029.

Planned completion: Jan 8, 2029. Time left: 2 years 2 months

Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 3396), which also shows the latest inspection date and photos.

Facts

Status
Under construction
Official progress
5.6%, as published by the Dubai Land Department
Planned completion
Jan 8, 2029
Construction start
Mar 3, 2025
Units
75
Buildings
1
Developer
Dubai Peninsula
Community
Jumeirah Second
Escrow bank
Emirates NBD Bank
DLD project number
3396

The register describes it as: "2B+G+1 Shared- Tower A (G+22+2R),Tower B(G+29+2R)"

Progress as the register reported it

SinceProgressPlanned completion
Oct 29, 20265.6%Jan 8, 2029

Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.

Off-plan sales registered

62 off-plan sales in Peninsula Dubai Residences - Tower 1 have been registered with the Dubai Land Department, worth AED 1.67 billion in all, the first on May 30, 2025 and the latest on May 4, 2026. The median price over the last 12 months was AED 77,133 per square meter (AED 7,166 per square foot).

Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.

More in Jumeirah Second