R Home MH
R Home MH is a building project in Bukadra, Dubai, by Bukadra Development. The Dubai Land Department's register puts it at 1.78% complete, with planned completion on Aug 31, 2029.
Planned completion: Aug 31, 2029. Time left: 2 years 10 months
Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 4214), which also shows the latest inspection date and photos.
Facts
- Status
- Under construction
- Official progress
- 1.78%, as published by the Dubai Land Department
- Planned completion
- Aug 31, 2029
- Construction start
- Mar 31, 2026
- Units
- 190
- Buildings
- 1
- Developer
- Bukadra Development
- Master developer
- Meydan Group
- Community
- Bukadra
- Escrow bank
- Abu Dhabi Commercial Bank
- DLD project number
- 4214
The register describes it as: "Residential Building G+3P+20+R floors"
Progress as the register reported it
| Since | Progress | Planned completion |
|---|---|---|
| Oct 29, 2026 | 1.78% | Aug 31, 2029 |
Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.
Off-plan sales registered
52 off-plan sales in R Home MH have been registered with the Dubai Land Department, worth AED 100 million in all, the first on Apr 29, 2026 and the latest on Oct 12, 2026. 3 of them in the last 90 days. The median price over the last 12 months was AED 27,390 per square meter (AED 2,545 per square foot).
Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.
More in Bukadra
- Skyvue Bukadra · Sobha 10.54%Planned completion Mar 31, 2030
- Skyscape Bukadra · Sobha 38.27%Planned completion Dec 31, 2029
- 310 Riverside Crescent Bukadra · Sobha 50.23%No planned date in the register
- 360 Riverside Crescent Bukadra · Sobha 50.67%No planned date in the register
- 340 Riverside Crescent Bukadra · Sobha 55.02%No planned date in the register
- 330 Riverside Crescent Bukadra · Sobha 67.81%No planned date in the register