Riva Residence
Riva Residence is a building project in Dubai Maritime City, Dubai, by Vakson First Property Development. The Dubai Land Department's register puts it at 100% complete (completed), with planned completion on Sep 25, 2025.
Completed on Dec 26, 2025, against a planned date of Sep 25, 2025.
Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 3034), which also shows the latest inspection date and photos.
Facts
- Status
- Completed
- Official progress
- 100%, as published by the Dubai Land Department
- Planned completion
- Sep 25, 2025
- Construction start
- Nov 1, 2022
- Units
- 155
- Buildings
- 1
- Developer
- Vakson First Property Development
- Master developer
- Dubai Maritime City
- Community
- Dubai Maritime City, in DLD's area Madinat Dubai Almelaheyah
- Escrow bank
- United Bank Limited (management Office)
- DLD project number
- 3034
The register describes it as: "B+G+4P+25 Residential Building & retails .The project designed to have a concrete structure and block with internal and external finishes."
Progress as the register reported it
| Since | Progress | Planned completion |
|---|---|---|
| Oct 29, 2026 | 100% | Sep 25, 2025 |
Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.
Off-plan sales registered
107 off-plan sales in Riva Residence have been registered with the Dubai Land Department, worth AED 276 million in all, the first on May 31, 2024 and the latest on Dec 22, 2025. The median price over the last 12 months was AED 24,798 per square meter (AED 2,304 per square foot).
Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.
More in Dubai Maritime City
- Breez by Danube Dubai Maritime City · Danube 0.14%Planned completion Jun 30, 2029
- Chelsea Residences 2 by Damac Dubai Maritime City · Damac 5.44%Planned completion Dec 31, 2029
- Oceanz 2 by Danube Dubai Maritime City · Danube 42.03%No planned date in the register
- Chelsea Residences by Damac Dubai Maritime City · Damac 5.19%Planned completion Dec 31, 2029
- Mar Casa Dubai Maritime City · Deyaar 56.45%Planned Oct 31, 2026, 7 days ago
- Franck Muller Yachting Dubai Maritime City · London Gate 0%Planned completion Jul 29, 2028