Samana IVY Gardens 2
Samana IVY Gardens 2 is a building project in Dubai Land Residence Complex, Dubai, by Samana International Real Estate Development. The Dubai Land Department's register puts it at 20.03% complete, with planned completion on Dec 31, 2027.
Planned completion: Dec 31, 2027. Time left: 1 year 2 months
Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 2909), which also shows the latest inspection date and photos.
Facts
- Status
- Under construction
- Official progress
- 20.03%, as published by the Dubai Land Department
- Planned completion
- Dec 31, 2027
- Construction start
- Jul 1, 2024
- Units
- 843
- Buildings
- 1
- Developer
- Samana International Real Estate Development
- Master developer
- Dubai Land Residences
- Community
- Dubai Land Residence Complex, in DLD's area Wadi Al Safa 5
- Escrow bank
- Dubai Islamic Bank
- DLD project number
- 2909
The register describes it as: "B+G+4P+35+ROOF.The project designed to have a concrete structure and block with internal and external finishes."
Progress as the register reported it
| Since | Progress | Planned completion |
|---|---|---|
| Oct 29, 2026 | 20.03% | Dec 31, 2027 |
Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.
Off-plan sales registered
853 off-plan sales in Samana IVY Gardens 2 have been registered with the Dubai Land Department, worth AED 810 million in all, the first on Jun 28, 2024 and the latest on Oct 1, 2026. 8 of them in the last 90 days. The median price over the last 12 months was AED 17,810 per square meter (AED 1,655 per square foot).
Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.
More in Dubai Land Residence Complex
- Peace Lagoons by Peace Homes Dubai Land Residence Complex · Peace Homes 4.16%Planned completion Sep 30, 2028
- Peace Lagoons II by Peace Homes Dubai Land Residence Complex · Peace Homes 4.04%Planned completion Jan 1, 2029
- Cove Living Residence by Imtiaz Dubai Land Residence Complex · Imtiaz 47.21%Planned completion Apr 15, 2027
- Sky Line by Peace Homes Dubai Land Residence Complex · Peace Homes 0%Planned completion May 30, 2030
- Samana Boulevard Heights Dubai Land Residence Complex · Samana 2.5%Planned completion Dec 31, 2028
- Cove Grand Residence by Imtiaz Dubai Land Residence Complex · Imtiaz 13.4%Planned completion Dec 15, 2027
More by Samana
- Samana Resorts International Media Production Zone · Samana 5.89%Planned completion May 30, 2028
- Samana Barari Heights Majan · Samana 4.04%Planned completion Oct 31, 2028
- Samana Barari Views Majan · Samana 26.81%Planned completion Mar 31, 2027
- Samana Barari Views 2 Majan · Samana 19.65%No planned date in the register
- Samana Barari Lagoons Majan · Samana 16.52%Planned completion Mar 31, 2028
- Samana Sky Views International Media Production Zone · Samana 2.23%Planned completion Jul 31, 2028