Serenia Living
Serenia Living is a building project in Palm Jumeirah, Dubai, by Palma Homes Real Estate Development. The Dubai Land Department's register puts it at 100% complete (completed), with planned completion on Dec 31, 2025.
Completed on Apr 23, 2026, against a planned date of Dec 31, 2025.
Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 2420), which also shows the latest inspection date and photos.
Facts
- Status
- Completed
- Official progress
- 100%, as published by the Dubai Land Department
- Planned completion
- Dec 31, 2025
- Construction start
- Jun 1, 2022
- Units
- 226
- Buildings
- 5
- Developer
- Palma Homes Real Estate Development
- Master developer
- The Palm - Jumeirah Co
- Community
- Palm Jumeirah
- Escrow bank
- Sharjah Islamic Bank
- DLD project number
- 2420
The register describes it as: "04 Residential Building with Shared Parking Basement (Tower 1 (G+17+R) + Tower 2 (G+19+R) + Tower 3 (G+14+R) + Tower 4 (G+12+R) + Landscape in Ground Floor with Future Swimming Pool. The project designed to have a concrete structure and block with internal and external finishes."
Progress as the register reported it
| Since | Progress | Planned completion |
|---|---|---|
| Oct 29, 2026 | 100% | Dec 31, 2025 |
Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.
Off-plan sales registered
334 off-plan sales in Serenia Living have been registered with the Dubai Land Department, worth AED 3.73 billion in all, the first on Sep 28, 2022 and the latest on Apr 21, 2026. The median price over the last 12 months was AED 49,976 per square meter (AED 4,643 per square foot).
Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.
More in Palm Jumeirah
- Passo by Beyond Palm Jumeirah · Estate Grand Real Estate Development 0%Planned completion Dec 31, 2029
- Palm Beach Towers -3 Palm Jumeirah · The Palm - Jumeirah Co 74.27%Planned completion Dec 31, 2026
- Palm Beach Towers - 2 Palm Jumeirah · The Palm - Jumeirah Co 81.56%Planned completion Dec 31, 2026
- Palm Beach Towers -1 Palm Jumeirah · The Palm - Jumeirah Co 82.83%Planned completion Dec 31, 2026
- The Alba Residences by Omniyat Palm Jumeirah · Grandeur Beach Real Estate Development 8.35%Planned completion Mar 31, 2028
- Olaia Residences Palm Jumeirah · Gulf House Real Estate Development 14.31%Planned completion Dec 31, 2027