16.15%complete

South Garden C

South Garden C is a building project in Wasl Gate, Dubai, by Jag Development. The Dubai Land Department's register puts it at 16.15% complete, with planned completion on Dec 31, 2027.

Planned completion: Dec 31, 2027. Time left: 1 year 2 months

Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 3141), which also shows the latest inspection date and photos.

Facts

Status
Under construction
Official progress
16.15%, as published by the Dubai Land Department
Planned completion
Dec 31, 2027
Construction start
Jan 1, 2025
Units
258
Buildings
1
Developer
Jag Development
Community
Wasl Gate, in DLD's area Jabal Ali First
Escrow bank
Emirates NBD Bank
DLD project number
3141

The register describes it as: "B+G+2 Podium+12 Floors Residential & commercial building. The project designed to have a concrete structure and block with internal and external finishes."

Progress as the register reported it

SinceProgressPlanned completion
Oct 29, 202616.15%Dec 31, 2027

Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.

Off-plan sales registered

255 off-plan sales in South Garden C have been registered with the Dubai Land Department, worth AED 334 million in all, the first on Jan 17, 2025 and the latest on Oct 30, 2026. 5 of them in the last 90 days. The median price over the last 12 months was AED 13,136 per square meter (AED 1,220 per square foot).

Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.