100%complete

Sunrise Living at Jumeirah Park

Sunrise Living at Jumeirah Park is a villa project in Jumeirah Park, Dubai, by Sunrise Valley. The Dubai Land Department's register puts it at 100% complete (completed), with planned completion on Jul 15, 2025.

Completed on Jun 25, 2026, against a planned date of Jul 15, 2025.

Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 2935), which also shows the latest inspection date and photos.

Facts

Status
Completed
Official progress
100%, as published by the Dubai Land Department
Planned completion
Jul 15, 2025
Construction start
Jan 15, 2024
Developer
Sunrise Valley
Master developer
Nakheel .(P J S C)
Community
Jumeirah Park, in DLD's area Al Thanyah Fifth
Escrow bank
Emirates NBD Bank
DLD project number
2935

The register describes it as: "41 Residential villas (G+1+R)"

Progress as the register reported it

SinceProgressPlanned completion
Oct 29, 2026100%Jul 15, 2025

Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.