Taormina Village 1
Taormina Village 1 is a villa community in Wadi Al Safa 3, Dubai, by Reportage Prime Properties. The Dubai Land Department's register puts it at 20.4% complete, with planned completion on Dec 20, 2027.
Planned completion: Dec 20, 2027. Time left: 1 year 1 month
Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 3108), which also shows the latest inspection date and photos.
Facts
- Status
- Under construction
- Official progress
- 20.4%, as published by the Dubai Land Department
- Planned completion
- Dec 20, 2027
- Construction start
- Dec 21, 2024
- Villas
- 530
- Developer
- Reportage Prime Properties
- Master developer
- Dubai Properties
- Community
- Wadi Al Safa 3
- Escrow bank
- Commercial Bank of Dubai(psc)
- DLD project number
- 3108
The register describes it as: "530 (G+2F+R) Villas.The project designed to have a concrete structure and block with internal and external finishes."
Progress as the register reported it
| Since | Progress | Planned completion |
|---|---|---|
| Oct 29, 2026 | 20.4% | Dec 20, 2027 |
Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.
Off-plan sales registered
307 off-plan sales in Taormina Village 1 have been registered with the Dubai Land Department, worth AED 709 million in all, the first on Oct 31, 2024 and the latest on Oct 29, 2026. 46 of them in the last 90 days. The median price over the last 12 months was AED 26,040 per square meter (AED 2,419 per square foot).
Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.
More in Wadi Al Safa 3
More by Reportage
- Verdana Residence 4 Dubai Investment Park First · Reportage 0.04%Planned completion Sep 30, 2028
- Verdana Residence 5 Dubai Investment Park First · Reportage 0%Planned completion Sep 30, 2028
- Verdana Residence 7 Dubai Investment Park First · Reportage 0%Planned completion Dec 31, 2028
- Verdana Residence 6 Dubai Investment Park First · Reportage 0%Planned completion Dec 30, 2028
- Verdana Residence 3 Dubai Investment Park First · Reportage 0.04%Planned completion Sep 30, 2028
- Verdana Residence 2 Dubai Investment Park First · Reportage 20.01%Planned Apr 30, 2026, 6 months ago