The Baltimore
The Baltimore is a building project in Town Square, Dubai, by Nshama Properties. The Dubai Land Department's register puts it at 26.33% complete, with planned completion on Sep 30, 2027.
Planned completion: Sep 30, 2027. Time left: 11 months
Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 3365), which also shows the latest inspection date and photos.
Facts
- Status
- Under construction
- Official progress
- 26.33%, as published by the Dubai Land Department
- Planned completion
- Sep 30, 2027
- Construction start
- May 18, 2025
- Units
- 167
- Buildings
- 1
- Developer
- Nshama Properties
- Community
- Town Square, in DLD's area Al Yelayiss 2
- Escrow bank
- First Abu Dhabi Bank
- DLD project number
- 3365
The register describes it as: "Residential Apartment G+P+15+R+Parking in Ground Floor & Podium Floor ."
Progress as the register reported it
| Since | Progress | Planned completion |
|---|---|---|
| Oct 29, 2026 | 26.33% | Sep 30, 2027 |
Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.
Off-plan sales registered
167 off-plan sales in The Baltimore have been registered with the Dubai Land Department, worth AED 232 million in all, the first on Jan 29, 2025 and the latest on Oct 29, 2026. 9 of them in the last 90 days. The median price over the last 12 months was AED 17,444 per square meter (AED 1,621 per square foot).
Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.
More in Town Square
- Symphony Town Square · Nshama 73.16%No planned date in the register
- Grove Town Square · Nshama 40.69%No planned date in the register
- Belmont Town Square · Nshama 0%Planned completion Apr 30, 2029
- Evelyn on the Park Town Square · Nshama 0.02%Planned completion Feb 28, 2029
- Rosewell Town Square · Nshama 0.02%Planned completion Dec 31, 2028
- Lana on the Park Town Square · Nshama 35.93%No planned date in the register
More by Nshama
- Haya on the Park Town Square · Nshama 35.33%Planned completion Feb 26, 2027
- Fia Town Square · Nshama 84.55%No planned date in the register
- Odessa Town Square · Nshama 8.01%Planned completion Dec 30, 2027
- Hillcrest Town Square · Nshama 38.36%Planned completion Jun 30, 2027
- Camden Town Square · Nshama 7.24%Planned completion Mar 31, 2028
- Ora Town Square · Nshama 47.38%No planned date in the register