The Chedi Private Residences
The Chedi Private Residences is a building project in Barsha Heights, Dubai, by Alseeb Real Estate Development. The Dubai Land Department's register puts it at 2.61% complete, with planned completion on Feb 28, 2029.
Planned completion: Feb 28, 2029. Time left: 2 years 4 months
Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 3323), which also shows the latest inspection date and photos.
Facts
- Status
- Under construction
- Official progress
- 2.61%, as published by the Dubai Land Department
- Planned completion
- Feb 28, 2029
- Construction start
- Mar 1, 2025
- Units
- 118
- Buildings
- 1
- Developer
- Alseeb Real Estate Development
- Master developer
- Dham
- Community
- Barsha Heights, in DLD's area Al Thanyah First
- Escrow bank
- Dubai Islamic Bank
- DLD project number
- 3323
The register describes it as: "Branded Residences with Ground Floor + 5 podiums + 44 Floors + 3 Mechanical Floors"
Progress as the register reported it
| Since | Progress | Planned completion |
|---|---|---|
| Oct 29, 2026 | 2.61% | Feb 28, 2029 |
Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.
Off-plan sales registered
73 off-plan sales in The Chedi Private Residences have been registered with the Dubai Land Department, worth AED 678 million in all, the first on Apr 23, 2025 and the latest on Dec 30, 2025. The median price over the last 12 months was AED 29,758 per square meter (AED 2,765 per square foot).
Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.