The Meriva Collection
The Meriva Collection is a building project in Palm Deira, Dubai, by Crestarc Developers. The Dubai Land Department's register puts it at 0.1% complete (not started), with planned completion on Dec 31, 2031.
Planned completion: Dec 31, 2031. Time left: 5 years 2 months
Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 4346), which also shows the latest inspection date and photos.
Facts
- Status
- Not started
- Official progress
- 0.1%, as published by the Dubai Land Department
- Planned completion
- Dec 31, 2031
- Construction start
- Apr 3, 2026
- Units
- 939
- Buildings
- 8
- Developer
- Crestarc Developers
- Master developer
- Nakheel .(P J S C)
- Community
- Palm Deira
- Escrow bank
- Sharjah Islamic Bank
- DLD project number
- 4346
The register describes it as: "(B+G+20 High Rise Residence) + 2X (B+G+10 Mid Rise Residence) + 2X (B+G+6 Residence) + (B+G+2 Residence) + (B+G+5 Hotel) + Supporting Amenities"
Progress as the register reported it
| Since | Progress | Planned completion |
|---|---|---|
| Oct 29, 2026 | 0.1% | Dec 31, 2031 |
Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.
Off-plan sales registered
513 off-plan sales in The Meriva Collection have been registered with the Dubai Land Department, worth AED 2.29 billion in all, the first on Apr 16, 2026 and the latest on Nov 5, 2026. 76 of them in the last 90 days. The median price over the last 12 months was AED 37,113 per square meter (AED 3,448 per square foot).
Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.
More in Palm Deira
- Hado by Beyond Palm Deira · Sandy Shores Real Estate L.L.C S.o.c 0.01%Planned completion Jun 30, 2029
- Ellington Sands I Palm Deira · Ellington 0.37%Planned completion Dec 31, 2028
- Ellington Sands II Palm Deira · Ellington 0.38%Planned completion Dec 31, 2028
- Bay Grove Residences C - Dubai Islands Palm Deira · Dubai Islands 7.29%Planned completion Apr 10, 2028
- Beach Residences Dubai Islands Palm Deira · Nakheel 28.8%No planned date in the register
- Edgewater Residences 3 Palm Deira · M G S Development 30.39%Planned completion Jan 31, 2027