16.64%complete

The Mural

The Mural is a building project in Dubai Maritime City, Dubai, by The Mural Real Estate. The Dubai Land Department's register puts it at 16.64% complete, with planned completion on Jul 10, 2028.

Planned completion: Jul 10, 2028. Time left: 1 year 8 months

Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 3650), which also shows the latest inspection date and photos.

Facts

Status
Under construction
Official progress
16.64%, as published by the Dubai Land Department
Planned completion
Jul 10, 2028
Construction start
Oct 10, 2025
Units
268
Buildings
1
Developer
The Mural Real Estate
Master developer
Dubai Maritime City
Community
Dubai Maritime City, in DLD's area Madinat Dubai Almelaheyah
Escrow bank
Commercial Bank of Dubai(psc)
DLD project number
3650

The register describes it as: "Residential-Retail (B+LG+G+2P+32FLOORS.) With Entertainment area @ First floor"

Progress as the register reported it

SinceProgressPlanned completion
Oct 29, 202616.64%Jul 10, 2028

Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.

Off-plan sales registered

266 off-plan sales in The Mural have been registered with the Dubai Land Department, worth AED 1.21 billion in all, the first on May 23, 2025 and the latest on Jun 23, 2026. The median price over the last 12 months was AED 54,414 per square meter (AED 5,055 per square foot).

Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.