The Palm Crown
The Palm Crown is a villa project in Palm Jumeirah, Dubai, by The Pointe. The Dubai Land Department's register puts it at 11% complete, with planned completion on Jul 15, 2027.
Planned completion: Jul 15, 2027. Time left: 8 months
Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 2954), which also shows the latest inspection date and photos.
Facts
- Status
- Under construction
- Official progress
- 11%, as published by the Dubai Land Department
- Planned completion
- Jul 15, 2027
- Construction start
- Jul 15, 2024
- Developer
- The Pointe
- Master developer
- Nakheel .(P J S C)
- Community
- Palm Jumeirah
- Escrow bank
- Dubai Islamic Bank
- DLD project number
- 2954
The register describes it as: "Development of 38 luxury villa, demolishing of existing buildings and infrastructure works within the development boundary"
Progress as the register reported it
| Since | Progress | Planned completion |
|---|---|---|
| Oct 29, 2026 | 11% | Jul 15, 2027 |
Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.
More in Palm Jumeirah
- Passo by Beyond Palm Jumeirah · Estate Grand Real Estate Development 0%Planned completion Dec 31, 2029
- Palm Beach Towers -3 Palm Jumeirah · The Palm - Jumeirah Co 74.27%Planned completion Dec 31, 2026
- Palm Beach Towers - 2 Palm Jumeirah · The Palm - Jumeirah Co 81.56%Planned completion Dec 31, 2026
- Palm Beach Towers -1 Palm Jumeirah · The Palm - Jumeirah Co 82.83%Planned completion Dec 31, 2026
- The Alba Residences by Omniyat Palm Jumeirah · Grandeur Beach Real Estate Development 8.35%Planned completion Mar 31, 2028
- Olaia Residences Palm Jumeirah · Gulf House Real Estate Development 14.31%Planned completion Dec 31, 2027