The Villa is a villa project in The Villa, Dubai, by Al Mazaya Holding Company. The Dubai Land Department's register puts it at 55.01% complete, with planned completion on Sep 11, 2013.
Planned completion was Sep 11, 2013. Time since: 13 years 2 months
Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 685), which also shows the latest inspection date and photos.
Facts
- Status
- Past planned completion
- Official progress
- 55.01%, as published by the Dubai Land Department
- Planned completion
- Sep 11, 2013
- Construction start
- Jul 17, 2008
- Buildings
- 1
- Villas
- 1
- Developer
- Al Mazaya Holding Company
- Master developer
- Dubai Properties
- Community
- The Villa, in DLD's area Wadi Al Safa 5
- DLD project number
- 685
The register describes it as: "Freehold residential villa development located at Dubai land (The Villa Project). The development originally consisted of 516 villas designed as a G+1 designed to be constructed as a concrete structure and concrete blocks with cement render finish."
Progress as the register reported it
| Since | Progress | Planned completion |
|---|---|---|
| Oct 29, 2026 | 55.01% | Sep 11, 2013 |