Verdana Residence is a building project in Dubai Investment Park First, Dubai, by Reportage Prime Properties. The Dubai Land Department's register puts it at 96.14% complete, with planned completion on Dec 31, 2025.
Planned completion was Dec 31, 2025. Time since: 10 months
Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 2470), which also shows the latest inspection date and photos.
Facts
- Status
- Past planned completion
- Official progress
- 96.14%, as published by the Dubai Land Department
- Planned completion
- Dec 31, 2025
- Construction start
- Dec 31, 2022
- Units
- 224
- Buildings
- 1
- Developer
- Reportage Prime Properties
- Master developer
- Dubai Investments Park Development Co
- Community
- Dubai Investment Park First
- Escrow bank
- Arab Bank For Investment & Foreign Trade Almasref
- DLD project number
- 2470
The register describes it as: "2B +G+ 10 FLOOR Residential , The project designed to have a concrete structure and block with internal and external finishes."
Progress as the register reported it
| Since | Progress | Planned completion |
|---|---|---|
| Oct 29, 2026 | 96.14% | Dec 31, 2025 |
Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.
Off-plan sales registered
211 off-plan sales in Verdana Residence have been registered with the Dubai Land Department, worth AED 108 million in all, the first on Jul 12, 2023 and the latest on Oct 28, 2026. 3 of them in the last 90 days. The median price over the last 12 months was AED 10,694 per square meter (AED 994 per square foot).
Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.
More in Dubai Investment Park First
- The Royal Estates PLOT.2 Dubai Investment Park First · Aristocrat Star Real Estate Development 23.75%Planned Dec 31, 2017, 8 years 10 months ago
- Verdana Residence 4 Dubai Investment Park First · Reportage 0.04%Planned completion Sep 30, 2028
- Verdana Residence 5 Dubai Investment Park First · Reportage 0%Planned completion Sep 30, 2028
- Verdana Residence 7 Dubai Investment Park First · Reportage 0%Planned completion Dec 31, 2028
- Verdana Residence 6 Dubai Investment Park First · Reportage 0%Planned completion Dec 30, 2028
- Verdana Residence 3 Dubai Investment Park First · Reportage 0.04%Planned completion Sep 30, 2028
More by Reportage
- Verdana Residence 2 Dubai Investment Park First · Reportage 20.01%Planned Apr 30, 2026, 6 months ago
- Verdana Residence 8 Dubai Investment Park First · Reportage 0%Planned completion Dec 31, 2028
- Verdana Residence 10 Dubai Investment Park First · Reportage 0%Planned completion Mar 31, 2029
- Verdana (Phase 1) Dubai Investment Park First · Reportage 94.62%Planned Dec 31, 2025, 10 months ago
- Verdana(Phase 2) Dubai Investment Park First · Reportage 93.96%Planned Dec 31, 2025, 10 months ago
- Bianca Wadi Al Safa 2 · Reportage 56.13%Planned completion Dec 31, 2026