Vincitore Aqua Flora is a building project in Dubai Science Park, Dubai, by Vincitore Luxury Real Estate Development. The Dubai Land Department's register puts it at 1.28% complete, with planned completion on Jun 30, 2028.
Planned completion: Jun 30, 2028. Time left: 1 year 8 months
Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 3154), which also shows the latest inspection date and photos.
Facts
- Status
- Under construction
- Official progress
- 1.28%, as published by the Dubai Land Department
- Planned completion
- Jun 30, 2028
- Construction start
- Jan 1, 2025
- Units
- 546
- Buildings
- 1
- Developer
- Vincitore Luxury Real Estate Development
- Master developer
- Dham
- Community
- Dubai Science Park, in DLD's area Al Barshaa South Second
- Escrow bank
- Mashreq Bank Psc
- DLD project number
- 3154
The register describes it as: "G+4P+15+Roof Retail, Residential Building"
Progress as the register reported it
| Since | Progress | Planned completion |
|---|---|---|
| Oct 29, 2026 | 1.28% | Jun 30, 2028 |
Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.
Off-plan sales registered
405 off-plan sales in Vincitore Aqua Flora have been registered with the Dubai Land Department, worth AED 512 million in all, the first on Dec 9, 2024 and the latest on Nov 2, 2026. 19 of them in the last 90 days. The median price over the last 12 months was AED 19,148 per square meter (AED 1,779 per square foot).
Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.
More in Dubai Science Park
- Skyhills Astra by HRE Dubai Science Park · HRE Real Estate Development 47.07%Planned completion Jun 30, 2028
- Binghatti Hills Dubai Science Park · Binghatti 90%No planned date in the register
- Binghatti Hillviews Dubai Science Park · Binghatti 32.6%Planned Apr 1, 2026, 7 months ago
- Vincitore Aqua Dimore Dubai Science Park · Vincitore 14.07%No planned date in the register
- SAAS Hills Dubai Science Park · Saas Properties L.L.C - Dubai Branch 12.98%Planned completion Mar 31, 2027
- 11 Hills Park Dubai Science Park · Townx Real Estate Development 80.05%Planned completion Mar 31, 2027